A task dependency makes a task wait for other tasks. The waiting task shows Blocked until every task it's blocked by is complete. Work order settings on its module can stop it from being worked on even after that, as described in How blocking works.

Before you begin

  • The tasks you want to link must already exist in the project.

Add a dependency

  1. Go to Projects and open the project.

  2. Select the task you want to link. It opens in a side panel on its Details tab.

  3. Under Dependencies, select Add Dependency. A new row appears with two dropdowns.

  4. In the first dropdown, choose the type:

    • Blocked By (the default): this task waits for the task you pick.

    • Blocks: the task you pick waits for this task.

  5. In the second dropdown, choose the task. Tasks are grouped by module, and you can search by name.

The dependency saves as soon as you choose a task. To make a task wait on more than one task, repeat steps 3 to 5. It stays Blocked until all of them are complete.

The picker lists the project's other tasks that aren't already linked on another row, so you can link tasks in different modules. It leaves out the task you're editing. When the type is Blocked By, the row shows the chosen task's current status. To open the linked task, select the arrow button on its row.

OnRamp won't save a dependency that forms a loop, such as task A waiting on task B while task B waits on task A. It also won't save one that repeats an existing pair. When that happens, the row shows Please select another task for this dependency. Choose a different task.

How blocking works

  • A blocked task can't be worked on or completed until the tasks it depends on are finished.

  • A task that's already complete isn't moved back to Blocked when you add a dependency.

  • When the last task it waits on is completed, the task leaves Blocked. It goes back to In Progress if it had been started, or to Not Started if not.

  • When a task is unblocked, its assignee and anyone it's restricted to get an email. If the task's scheduled start date is in the future, the email isn't sent unless your organization's settings allow it.

  • If a task that others depend on is re-opened or reset, the open tasks waiting on it go back to Blocked. Waiting tasks that are already complete stay complete.

  • Work order settings on a module can also stop a task from being worked on after its dependencies are met. On that task, a work order message appears in place of its subtasks. See Control task order in a module with work order settings.

For more on what each status means, see How task statuses work.

Change or remove a dependency

  • To change a dependency, choose a different type or task on its row. The change saves in place.

  • To remove a dependency, select the trash icon on its row. In the Delete Task Dependency dialog, select Delete Dependency.

If the dependency you remove was still unmet, the waiting task leaves Blocked, as long as nothing else blocks it.

Find what's blocking a task

  1. Open the blocked task.

  2. Select the Subtasks & Responses tab. It lists the tasks blocking this one.

  3. Optional: To review them, select See Dependencies. It takes you to Dependencies on the Details tab. Automated tasks don't show this button.

You can also check Dependencies on the Details tab, which shows the status of each Blocked By task.

See dependencies on the Gantt chart

In the project, select the Gantt tab. Lines connect linked tasks, and the Dependencies column shows how many dependencies each task has. For more, see Using the project Gantt chart.

Set dependencies in a playbook or module

Playbook tasks and Library module tasks have the same Dependencies section in their task panel, with the same Add Dependency control. Set dependencies there, and every project built from them starts with those dependencies already set. To learn how edits to linked modules reach playbooks and projects, see Build reusable linked modules.