Project progress

Updated

Project progress is the share of a project's tasks that are complete, shown as a percentage. OnRamp works it out for you, so it's never set by hand. For example, a project with 5 of its 10 tasks complete shows 50%.

When to use it

Use progress to see how far along a project is and how much work is left. On the projects list, you can compare many projects at once and filter for projects that are just starting or nearly done.

How it works

How the number is worked out

Progress counts the project's tasks across all its modules, then divides the completed tasks by the total. The result is a whole-number percentage:

  • A project with no tasks shows 0%.

  • A project where every task is complete shows 100%.

  • Deleted tasks aren't counted.

The percentage updates on its own when a task is completed, and when tasks are added to or removed from the project. Adding tasks can lower the percentage. Completing tasks raises it.

Where you see it

  • Projects list: each project shows a progress bar and a percentage in the Progress column.

  • Inside a project: the project overview shows Progress for tasks across all modules.

  • Modules: each module has its own completion percentage, recounted when its tasks change. It shows as a progress circle labeled Progress in the module slideout, which turns into a complete icon at 100%, and as a progress ring on the project's Responses tab.

Progress in the customer portal

Customer users see a progress percentage in the customer portal, and it can differ from the one your team sees. Customer progress leaves out tasks hidden from the portal with the task's visibility setting. Every other task counts. To choose which tasks are hidden, see Task visibility in the customer portal.

For example, take a project with 10 tasks:

  • 5 tasks hidden from the portal

  • 3 internal tasks shown in the portal with restricted details

  • 2 customer tasks

When the 2 customer tasks are complete, your team sees 2 of 10 tasks complete, or 20%. Customer users see 2 of 5 tasks complete, or 40%.

The customer-facing percentage also appears in the embedded widget, as percent_complete. See the Widget API reference.

Filter projects by progress

On the projects list, the Progress filter compares against the whole-number percentage in the Progress column. It offers less than, greater than and equals a percentage. For example, Progress greater than 75 finds projects close to done.

The Projects page also has a Nearing completion headline card that counts active projects at 75% progress or more. Selecting it applies a Progress greater than 74 filter, so the list can also include projects that aren't active. To learn more about the headline cards, see the Projects Overview Page. To keep a filter for later, see Save and reuse project and task filters.

Act when progress reaches a threshold

A project automation can run when the project's progress rises to a threshold between 1 and 100 from below it. If progress drops below the threshold, for example because tasks were added, and then rises to it again, the automation runs again. The trigger is Project completion % reached, and by default it uses the customer-facing percentage. To set one up, see Create project automations.

Limits

  • Every task counts the same, however much work it involves.

  • Progress shows how many tasks are done, not whether the project is on schedule.

  • Customer progress isn't limited to tasks customers can open. Only tasks hidden with the visibility setting are left out.