Project Pipeline
Updated
The Project Pipeline view in Insights answers one question: of the projects you expected to complete in a period, what actually happened to them? It shows how many were completed, added, pulled in, pushed out, archived or still open at the end.
When to use it
To see whether the projects planned for this month, or another period, closed on schedule.
To spot projects whose planned completion moved out of the period.
To see the value at stake. Switch the chart to Total Project Value to see slippage in contract value rather than project count.
To compare owners. Open Group by, select Owner, and then select Apply.
To open the view, go to Insights > Capacity & Planning > Project Pipeline.
How it works
Which projects are counted
The date filter is labeled Projects ending during, and it starts on this month. A project appears when its planned end date was in that window when the period started, or is in it now. A project completed during the period also appears, whatever its end date. So does a project archived during the period, but only when Archived is selected under Statuses.
Pipeline stages
Each project is counted in the stages that describe what happened to it:
Stage | What it counts |
|---|---|
Opening | Projects already planned to complete during the period when the period started. |
Created | Projects created during the period that are also planned to complete within it. Shown in green as an addition. |
Pulled in | Existing projects whose planned completion date was moved into the period after it started. It also counts projects completed or archived in the period that don't otherwise qualify. They don't have to be completed. |
Completed | Projects completed during the period. Shown as a subtraction, because they leave the pipeline. |
Archived | Projects that weren't completed but were archived during the period. |
Pushed out | Projects planned to complete in the period whose planned completion date was moved beyond it. |
Ending | Projects still incomplete at the end of the period. |
To read these definitions in the app, select the info icon next to the metric dropdown. It opens About the project pipeline report.
The waterfall chart
The top chart shows the flow of planned versus actual completion for the period, one bar per stage. Hover over a bar to see its exact count, for example "Created: 16".
Use the dropdown at the top right of the chart to switch between Project Count and Total Project Value.
The chart toolbar has Restore, which resets the chart view, and Save as Image, which downloads the chart.
The Sankey diagram
The Sankey diagram shows flows from three origins (Opening, Created and Pulled in) to the outcomes Completed, Archived, Pushed out and Ending. Each node shows its count, for example "Completed: 8".
The summary bar
The summary bar lists every stage with a signed count, for example +16 for Created and -6 for Completed.
The Projects table
Under the charts, the Projects table lists every project in the report. It shows how many projects it's showing, and you can sort by any column:
Project, Account, Owner, Value and Health
Current Start, Original Start, Current End and Original End
Completed Date and Archived Date
Start Variance, End Variance and Status
Use the column picker to hide columns or reset them. When Group by is set, rows sit under headers you can collapse.
To see the projects in one stage, select its bar in the waterfall chart or its node in the Sankey diagram. The table filters to that stage and shows a Stage: chip. To clear it, select Clear stage filter on the chip, or select the same stage again.
To open a project, select its row. The project slideout opens, and you can step through the other projects in the table from there.
Filters
Projects ending during: the period to report on.
Accounts and Owners: each shows All until you choose some.
Statuses: In Progress, Completed or Archived projects. When project holds are turned on for your organization, On hold is also offered. Only In Progress and Completed are selected at first. Archived projects are left out until you add Archived and select Apply. The Archived stage still appears, but it doesn't count archived projects until then. When project holds are turned on, on-hold projects are also left out until you add On hold and select Apply.
Data Field: filters projects by a data field's value. It appears when your organization has project data fields.
Group by: None, Owner, or an available data field.
Select Apply to apply your filters.
You can also ask Aero about the pipeline data. See Ask Aero in Insights.
Limits
The summary bar always shows project counts, even when Total Project Value is selected.
Restore resets the chart view. It doesn't refresh the data.
Group by has no option to group by status.
The Sankey diagram draws no ribbon for projects that entered the pipeline before the period. When every project did, it shows No flow connections to display.