Project Pipeline

Updated

The Project Pipeline view in Insights answers one question: of the projects you expected to complete in a period, what actually happened to them? It shows how many were completed, added, pulled in, pushed out, archived or still open at the end.

When to use it

  • To see whether the projects planned for this month, or another period, closed on schedule.

  • To spot projects whose planned completion moved out of the period.

  • To see the value at stake. Switch the chart to Total Project Value to see slippage in contract value rather than project count.

  • To compare owners. Open Group by, select Owner, and then select Apply.

To open the view, go to Insights > Capacity & Planning > Project Pipeline.

How it works

Which projects are counted

The date filter is labeled Projects ending during, and it starts on this month. A project appears when its planned end date was in that window when the period started, or is in it now. A project completed during the period also appears, whatever its end date. So does a project archived during the period, but only when Archived is selected under Statuses.

Pipeline stages

Each project is counted in the stages that describe what happened to it:

Stage

What it counts

Opening

Projects already planned to complete during the period when the period started.

Created

Projects created during the period that are also planned to complete within it. Shown in green as an addition.

Pulled in

Existing projects whose planned completion date was moved into the period after it started. It also counts projects completed or archived in the period that don't otherwise qualify. They don't have to be completed.

Completed

Projects completed during the period. Shown as a subtraction, because they leave the pipeline.

Archived

Projects that weren't completed but were archived during the period.

Pushed out

Projects planned to complete in the period whose planned completion date was moved beyond it.

Ending

Projects still incomplete at the end of the period.

To read these definitions in the app, select the info icon next to the metric dropdown. It opens About the project pipeline report.

The waterfall chart

The top chart shows the flow of planned versus actual completion for the period, one bar per stage. Hover over a bar to see its exact count, for example "Created: 16".

Use the dropdown at the top right of the chart to switch between Project Count and Total Project Value.

The chart toolbar has Restore, which resets the chart view, and Save as Image, which downloads the chart.

The Sankey diagram

The Sankey diagram shows flows from three origins (Opening, Created and Pulled in) to the outcomes Completed, Archived, Pushed out and Ending. Each node shows its count, for example "Completed: 8".

The summary bar

The summary bar lists every stage with a signed count, for example +16 for Created and -6 for Completed.

The Projects table

Under the charts, the Projects table lists every project in the report. It shows how many projects it's showing, and you can sort by any column:

  • Project, Account, Owner, Value and Health

  • Current Start, Original Start, Current End and Original End

  • Completed Date and Archived Date

  • Start Variance, End Variance and Status

Use the column picker to hide columns or reset them. When Group by is set, rows sit under headers you can collapse.

To see the projects in one stage, select its bar in the waterfall chart or its node in the Sankey diagram. The table filters to that stage and shows a Stage: chip. To clear it, select Clear stage filter on the chip, or select the same stage again.

To open a project, select its row. The project slideout opens, and you can step through the other projects in the table from there.

Filters

  • Projects ending during: the period to report on.

  • Accounts and Owners: each shows All until you choose some.

  • Statuses: In Progress, Completed or Archived projects. When project holds are turned on for your organization, On hold is also offered. Only In Progress and Completed are selected at first. Archived projects are left out until you add Archived and select Apply. The Archived stage still appears, but it doesn't count archived projects until then. When project holds are turned on, on-hold projects are also left out until you add On hold and select Apply.

  • Data Field: filters projects by a data field's value. It appears when your organization has project data fields.

  • Group by: None, Owner, or an available data field.

Select Apply to apply your filters.

You can also ask Aero about the pipeline data. See Ask Aero in Insights.

Limits

  • The summary bar always shows project counts, even when Total Project Value is selected.

  • Restore resets the chart view. It doesn't refresh the data.

  • Group by has no option to group by status.

  • The Sankey diagram draws no ribbon for projects that entered the pipeline before the period. When every project did, it shows No flow connections to display.