Project Schedule Timeline

Updated

The Project Schedule Timeline is an Insights page that lays your projects out on a timeline. Each project is a bar from its start date to its end date. A table under the chart shows how far each project's dates have moved from the original plan.

When to use it

Use it to see which projects run at the same time and how work is spread across owners. It also shows which projects have slipped from their original schedule. You can open and update a project from the page without leaving Insights.

How it works

To open it, go to Insights, then select Project Schedule Timeline under Capacity & Planning. You need permission to view Insights. Without it, you're sent to a no-access page.

Which projects appear

The timeline shows projects that match your filters and have a planned start date, a due date, or both in the date range. A project with no planned start date appears when its due date falls in the range. If none match, the chart reads No scheduled projects to display.

The Statuses filter starts with only In Progress selected. Projects in any other status stay hidden until you change it.

The date range

The date range control is labeled Projects scheduled during and starts on This quarter. Its presets include Next month. A project appears if its dates overlap the range, even if it starts before the range or ends after it. The range's from and to dates become the chart's left and right edges.

Bars and colors

Each bar shows the project's name, account and owner. A project with no account shows No Account, and one with no owner shows Unassigned. The bar fills in to match the project's completed percentage.

A bar's color follows this order:

Legend

Color

When it's used

Complete

Green

The project is in a completed status.

At Risk

Yellow

The project's health is At Risk.

Off Track

Red

The project's health is Off Track.

In Progress

Purple

Every other project.

At Risk and Off Track are health values, not statuses. To learn what sets them, see Project health and engagement.

When today falls inside the date range, a vertical NOW marker shows today's date. To see a project's details, hover over its bar. The tooltip shows its account, owner, start date, due date, progress and status.

Scale and fullscreen

To change the scale, select Week, Month or Quarter in the tabs above the chart. To make the chart fill the screen, select the Fullscreen icon at the top right of the chart. Select it again to exit.

Filters, grouping and sorting

  • Accounts, Owners and Statuses each filter by the values you check. Accounts and Owners show All until you pick values, then a count of the values selected. Statuses starts at 1 selected, because In Progress is preselected.

  • Data Field filters projects by the values of a data field. Pick a field, check the values to include, and select Apply. When the field has more than 8 values, a search box helps you find them. It appears only when your organization has data fields the page can use.

  • Group by groups the timeline by None, Owner, Status, or a data field listed under Data Fields.

  • Sort by orders projects by Start Date, Due Date or Progress.

To apply your filter changes, select Apply.

When the timeline is grouped, each group has a header with its project count. To collapse or expand a group, select its header.

The table

Under the chart, a table lists one project per row. Its columns are Project Name, Account, Owner, Value, Health, Current Start, Original Start, Start Variance, Current End, Original End, End Variance and Status. The Status column shows the same In Progress, At Risk, Off Track or Completed label as the bar color, not the project's own status. To sort by a column, select its header.

To hide or show columns, use the column picker in the table's header. To reorder a column, drag its header; Project Name stays in place. To resize a column, drag its edge.

Variance is shown in days. A negative number means the date moved earlier and shows in green. A positive number means it moved later and shows in red.

The bar at the bottom of the page shows Total, Off Track, At Risk and Avg Progress for the projects shown.

The project panel

To open a project's details, select its bar or its row in the table. A panel opens on the right with Project Name, Project Owner, Account and Description. For every seat license except Contributor, it also shows Start Date, End Date, Value, Affiliated Accounts and Status. Affiliated Accounts appears only when the project has affiliated accounts. On a project that isn't archived, Add affiliated account adds one. Your organization's project data fields follow. The panel also has a Recent Activities & Upcoming Tasks section.

To move to another project, use the arrows at the top of the panel. They step through the projects on the page, with a counter such as 5 / 24.

Limits

  • You can't add columns to the table. Data fields can filter and group projects, but they can't be added as columns. You can hide, reorder and resize the columns that are there.

  • The Statuses filter lists project statuses, so you can't filter by At Risk or Off Track there. Group by Status also groups by the project's own status. To find At Risk and Off Track projects, sort the Health or Status column, or look at the bar colors.

  • Editing in the panel is limited:

    • On an archived project, the start and end dates, value, affiliated accounts, account and status are locked. You can still edit the project name, owner, description and data fields.

    • Changing dates needs permission to update the project schedule.

    • You can't change the account when the project already has an account and active users. Contributors can't change it.

    • Changing data fields needs permission to manage data fields.