Use the project Gantt chart

Updated

Who can do this: People with permission to edit the project's tasks. Contributors can view the chart but can't add modules or tasks.

The Gantt chart shows a project's modules and tasks on a timeline, so you can see the schedule and change dates by dragging.

Before you begin

  • You can only change the timeline when the project isn't completed or archived.

Open the Gantt chart

  1. Go to a project.

  2. Select the Gantt tab at the top of the project.

The left panel lists the project's modules and the tasks in each one. Expand or collapse a module to focus on it. The right side is the timeline, where modules and tasks are plotted by their start and due dates. Each task is a horizontal bar running from its start date to its due date.

Each task bar shows its status, and overdue tasks get an overdue marker. A bar shows the assignee's picture, or the account logo when the task has no internal owner. A task with no dates appears on the project end date.

To open details, select a bar. A task bar opens the task's side panel, a module bar opens the module's panel, and the project bar opens the project dates panel.

Move or resize a task

  1. To move a task, drag its bar left or right. Its start and due dates update automatically.

  2. To make a task longer or shorter, drag the left or right edge of its bar.

Add or remove a dependency

Dependencies appear as lines connecting tasks.

  1. To add one, drag from the connector on one task bar to another task bar.

  2. If the new dependency moves other tasks, the You're adding a dependency dialog shows how many days the task's start date is pushed forward. Select Confirm.

  3. To remove a dependency, select its line, then select Confirm in the You're removing a dependency dialog.

Connectors only appear when you can edit the timeline.

When the project's dates are set to follow rules, the chart shows a key with Blocked by and Dates follow. Dates follow links are dashed, and you can't remove them by selecting them. Only Blocked by lines can be removed this way.

Control how dependent tasks move

The chart's header has two settings:

  • Settings: open the Options... dropdown and select Move dependent tasks as a group. Moving a task then shifts the tasks that depend on it.

  • Date Limits: limits where dependent tasks can start when you move them.

    • Unrestricted: tasks move freely.

    • Start Date: a dependent task can't start before the task blocking it starts.

    • End Date: a dependent task can't start before the task blocking it ends.

Add a module

You need permission to manage the project's modules.

  1. Select the + next to the project name (its tooltip reads Add module to project).

  2. Choose an option:

    • New Module: in the Create Module dialog, enter a Module Name and select Create.

    • Add from Library: in Choose from Library, select modules and then Add to Project. You need permission to view library modules.

Add a task

You need permission to create tasks in the project.

  1. Select the + next to a module (its tooltip reads Add task to module).

  2. Choose an option:

    • New Task

    • Add from Library: in Choose from Library, select tasks and then Add to module. You need permission to view library tasks.

Reorder tasks

To reorder tasks, drag rows in the left panel. This needs permission to edit the project's tasks and change item order. If a module you just added hasn't finished saving, the reorder is undone and you see an error.

Choose columns

  1. Select the + at the top of the task list to manage columns.

  2. Show or hide Assignee, Start Date, Due Date, Completion Date, Status, Progress, Dependencies, Subtasks and Visibility. Name is always shown.

Visibility shows either your organization's name followed by "only", or All Members.