Project Health Overview in Insights
Updated
The Project Health Overview in Insights shows how many of your projects are On Track, At Risk or Off Track. Health is based on the percentage of overdue tasks in each project. A project that uses automatic dates can also be At Risk when its projected end falls after its planned due date.
When to use it
Use this page to find projects with too many overdue tasks before they slip further. For example, use it in a weekly review, to check one owner's projects, or to report on overall project health.
How it works
Which projects appear
By default, the page shows In Progress projects that were active during this quarter. A project counts as active if it was running at any point in the date range. That means it started before the range ends, and its planned end date falls after the range begins. Long-running projects always appear. Projects without a planned start date or a planned due date don't appear.
Health statuses
Each project gets one of three health statuses:
On Track (green)
At Risk (orange)
Off Track (red)
The share of the project's tasks that are overdue sets the status. A project that would otherwise be On Track is At Risk when its projected end falls after its planned due date. This applies when automatic dates are turned on and the project uses them, and someone set its due date. For the full rule, see Project health and engagement.
The Project Health Distribution chart
A donut chart shows how your projects split across the three health statuses, with one colored segment each. Hover over a segment to see its label, project count and percentage, for example At Risk: 3 (12.5%).
To see only one health status, select its segment. The table switches to show just those projects, with a Health: chip above it. To remove the filter, select the same segment again or select the Clear health filter button on the chip. Applying other filters also clears it. You can filter to one health status at a time.
The All Projects table
Below the chart, the All Projects table lists the projects in the current view. It has these columns:
Project Name
Account
Owner
Health
Status: In Progress or Completed
Value
Planned Start
Planned Due
Actual Completion: the date the project was completed. It's empty for projects that aren't completed.
You can sort by any column. For example, sort by Health to bring At Risk and Off Track projects together, or by Value to see your largest projects first.
To open a project, select its row. The project slideout opens, and you can move between the projects shown in the table without closing it.
Summary metrics
At the bottom of the page, four metrics summarize the current view: Total Projects, On Track, At Risk and Off Track.
Projects without health data still count in Total Projects, but they don't appear in the chart. So Total Projects can be more than the other three added together. If no project in the view has health data, the chart shows No health data available.
Filters and grouping
The filter bar at the top of the page has these filters:
Projects active during: the date range
Accounts
Owners
Statuses: In Progress, Completed and Archived. When project hold is turned on for your organization, it also offers On hold, between In Progress and Completed. If you don't see it, contact your OnRamp team. Only In Progress is selected at first, so add Completed to include finished projects. Archived projects don't appear on this page, even when you select Archived.
A data field filter, when your organization has data fields
Changes to Accounts, Owners, Statuses and Group by take effect when you select Apply. Choosing a new date range, or selecting Apply in the data field filter, refreshes the page right away. Any other changes you've made are applied at the same time.
To group the table, use Group by, and then select Apply. You can group by None, Owner or Status. When your organization has data fields, you can also group by a data field.
Ask Aero
When Ask Aero is turned on for your organization and you have permission to use Aero, an Ask Aero button appears at the upper right of the page. To open the Ask Aero panel, select Ask Aero. It uses the chart's data, including your active filters and any health segment you've selected. It adds a note to the chat when you change filters.
Ask Aero offers these starter prompts:
Summarize this chart
Show immediate action items
What do the most at-risk projects have in common?
Which at-risk projects show signs of recovering on track?
You can also enter your own questions. To learn more, see Ask Aero in Insights.
Limits
There's no filter for playbook or for health status. To narrow to one health status, select its segment in the chart.
Health reflects overdue tasks and, for projects that use automatic dates, whether the projected end falls after the planned due date. It doesn't measure customer engagement.
Projects without health data don't appear in the chart.
The Ask Aero button appears only when Ask Aero is turned on for your organization and you have permission to use Aero. If you don't see it, contact your OnRamp team.