Task Performance is an Insights view that shows how individual tasks perform across your playbooks. It shows which tasks finish early, on time or late, so you can spot the bottleneck tasks inside a playbook.
When to use it
Use Task Performance when projects run late and you want to know which tasks are behind it. It's also useful after you change a playbook, to check whether a task now finishes on time more often.
How it works
The view compares each task's completion with its due date. The difference, in days, is the task's variance. A negative variance means the task finished early, and a positive one means it finished late.
A task needs a due date to have a variance. If none of the tasks in your filters have due dates, the chart shows No tasks with due dates. To learn how due dates are set, see Project dates and task scheduling.
The Task Completion Variance chart
The chart is titled Task Completion Variance. It has one row per task template. Each row's label shows the task and its playbook, plus how many tasks the row includes. The rows scroll, about ten at a time.
Each dot is one task instance:
Dots on the ← EARLY side, to the left, finished before their due date. Tasks that aren't complete are measured against today's date. So when the Status filter includes open tasks, an open task that isn't due yet also appears on this side.
Dots on the LATE → side, to the right, finished after their due date or are overdue. An overdue task that isn't complete yet is measured against today's date.
Dots in the ON TIME band finished on their due date.
A bar marks each row's average, and the row's average variance appears on the right.
Hover over a dot to see the project name, the variance in days, the due date, and either the completed date or In progress.
To drill down from the chart:
Select a dot to open that task in a slideout.
Select a row's average bar to filter the table to that task template. A chip shows the task's name. To remove it, select Clear filter on the chip.
The Task Performance by Playbook table
Under the chart, the Task Performance by Playbook table has one row per task template, with these columns:
Task Name: the task template's name.
Source From: the kind of source the task comes from.
Source Name: the playbook or other source the task belongs to.
Instances: how many times the task appears within the current filters.
Avg Variance: the average days early (negative) or late (positive).
Early, On Time and Late: how many instances finished in each band.
By default, the table is sorted by Instances, most first. To find the tasks that run latest, sort by Avg Variance instead. A task with a high average variance and many instances is a pattern across projects, not a one-off.
You can show, hide, reorder and resize columns. The table header shows how many templates and instances it includes.
Expand a row to list each instance, with Project, Account, Owner, Module, Tags, Task Status, Due Date, Completed and Variance. Select an instance to open the task in a slideout.
Summary metrics
At the bottom of the page, these metrics sum up the current view:
Task Templates
Total Instances
Avg Early
Avg Late
On-Time Rate
When dynamic task dates are turned on for your organization, a sixth metric appears: Finished by original due date.
To track the On-Time Rate over time, change the date range and compare the results.
Filters
The filter bar at the top has these filters:
Tasks active between: the date range. It starts at this quarter. It includes tasks that were created, started or completed within the range.
Status: only Completed is selected at first. Clear it to include tasks in other statuses, such as overdue tasks that aren't complete.
Accounts, Owners and Playbook: each can take more than one value. The Accounts and Owners lists only show entries with projects in the date range.
Module and Tags.
Under More are two further options:
Task type: All types, Internal or Customer.
Exclude tasks from archived projects & playbooks: on by default.
A change to the date range applies right away. Your other filter changes take effect when you select Apply in the filter bar. Applying filters also removes any task template chip from the table.
Ask Aero
The Ask Aero button appears only when Aero is turned on for your organization and you have permission to use Aero. If you don't see it, contact your OnRamp team. To ask questions about this view, select Ask Aero. The Aero panel uses this chart's data and your filters. It offers suggested questions, such as Which tasks are causing the most delay across projects?, and you can type your own. For more, see Ask Aero in Insights.
Limits
Tasks without a due date have no variance, so the chart can't plot them.
At first the view only counts Completed tasks. Overdue work only appears once you clear the Status filter.
Results are limited to the top 200 task templates. When that happens, a notice asks you to narrow your filters.
The view shows what's late, not why. Check the playbook and the project to find the cause.