Project health and engagement signals

Updated

Every project has two signals that show how it's going. Health is based on the share of the project's tasks that are overdue. Engagement is based on how recently anyone did something on the project.

When to use it

Use these signals to find projects that need attention before they fall further behind. Check them in Insights for a summary, or in a projects view for a live list you can work through.

How it works

Health

OnRamp calculates health from the share of the project's tasks that are overdue. You don't set it by hand. A project has one of three health statuses:

  • On Track: 19% or fewer of the project's tasks are overdue. If the project uses automatic dates and someone set a target date, its projected end must also be on or before that target.

  • At Risk: 20–60% of the project's tasks are overdue. A project that uses automatic dates is also At Risk when it would be On Track, but its projected end falls after a target date someone set.

  • Off Track: more than 60% of the project's tasks are overdue. A share above 19% but below 20%, such as 39 of 200 tasks, also shows Off Track.

Archived projects have no health. Putting projects on hold is available when it's turned on for your organization. If you don't see it, contact your OnRamp team. A project on hold has no health until it's resumed.

Engagement

Engagement is set from how many days have passed since the project's most recent recorded activity:

  • High: the last activity was 5 days ago or less.

  • Medium: the last activity was 6 to 10 days ago.

  • Low: the last activity was more than 10 days ago, or the project has no activity.

Activity by anyone on the project counts, including your team. So a project can show High engagement while its customer users haven't done anything.

Find projects that need attention

  • Insights: Go to Insights and select Project Health Overview under Health & Risks. The Project Health Distribution chart counts On Track, At Risk and Off Track projects. The Project Health Overview article covers the rest of this screen.

  • Views: Health and engagement are available as columns in any projects view. Filter a projects view to At Risk and Off Track health for a list you can check each day. On the projects page, the health filter is labeled Performance.

  • Views: Filter a projects view to Engagement = Low to find projects where nothing has happened for more than 10 days.

To ask questions about a report's data, use the Ask Aero panel in Insights. Ask Aero is available when it's turned on for your organization and you have permission to use Aero. If you don't see it, contact your OnRamp team. See Ask Aero in Insights.

Act on a signal

At Risk

  • Open the project and find the tasks that are overdue or blocked. Check whether task dependencies are holding work up.

  • Send a Nudge to the assignee of a task that's been sitting idle. See Send a nudge reminder about a task.

  • Review the project's dates and task scheduling if the timeline has shifted.

  • Check the Aero brief on the project's Overview for recommended actions, such as a nudge or a reassignment. The Aero brief is available when it's turned on for your organization. If you don't see it, contact your OnRamp team. See Aero project brief and actions.

Off Track

  • Reach out directly to the customer or the internal owner.

  • Use the Activity Log to see when progress stalled and what happened last.

Low engagement

  • Check when customer users last visited the portal. Go to Insights and select Portal Engagement under Engagement. The table shows one row per project. Expand a project's row to see each customer user's Last Visit, Login Status and Last Action.

  • Send a Nudge on a key customer task to prompt them. You can nudge a customer task only while the project's portal is live and customer emails are turned on for the project. Customer emails also can't be paused for all customers in your organization's notification settings.

  • Check that the right customer contacts are on the project.

Limits

  • Health only reflects overdue tasks and, for projects with automatic dates, the projected end against a target date. It doesn't account for anything else about the account.

  • Engagement doesn't separate your team's activity from your customers'. For customer activity on its own, use Portal Engagement in Insights.

  • Archived projects and projects on hold have no health.